St Giles
Church Codicote - Roof repairs - Spring 2002
The
new roof Complete!
3rd
July - all the woodwork is complete - first delivery of lead arrived on
site today
14th
June - all the rafters are now back in place
28th
May - The rafters begin to go back into place - a mixture of old and new
ones.
28th
May - The new ridge beam is in place.
28th
May - The tiles are now back on the chapel and chancel roofs.
18th
May - The new wall plates for the North wall are in place.
18th
May - The chancel and chapel roofs have been felted and battened - the
tiles are ready to put on
15th
May - a new lead valley gutter has been installed between chancel and
chapel.
15th
May - the old ridge has been removed
15th
May - all the old rafters have now been removed
10th
May - the old rafters begin to be removed
27th
April - Repairs to the gable end are complete!
20th
April The Cross is returned to the top of the gable end.
19th
April - Main ridge beam. Note the side beams do not connect with the ridge.
19th
April - reconstruction of the gable end nearing completion - shuttering
is being removed.
9th April 2002
- work underway to reconstruct the gable end of the Nave above the Chancel.
A brick lining is being constructed and this will carry a flint exterior
26th March 2002
26th March 2002
Work begins to demolish the
top of the wall between Nave and Chancel which is "live".
26 February 2002
Further damage to a main
beam - under the metal strapping
26 February 2002
The ladder is in one of the
bays damaged by fire 30 or 40 years ago. All rafters here need to be
replaced in oak.
26 February 2002
One of the main roof support
beams
26 February 2002
The end where the panel fell
from - note side rafters (under the wooden panel) do not reach the ridge
beam.