2007 Roof Work
Work Started 12th
June 2007
|
|
Thursday 5th July
Scaffold on the tower nearly
complete
|
 |
|
|
Tuesday 10th July
Work gets underway on the tower
Weathervane removed. Substantial
loss of integrity to metalwork. Timber boss decayed on underside and split
- replacement required.
Spire mast: Extensive decay
and beetle attack evident in top section.
|
 |
 |
|
Thursday 12th July
Work continues on the tower.
The edge of the gutter is breaking away from the wall
|
 |
 |
| The
exit from the inside of the tower and a closer picture of the edges of the
internal gutter |
 |
 |
| Parts
of the clerstory wall are being repointed. |
 |
 |
|
Friday 20th July 2007
Repointing work continues
on the clerstory wall
|
 |
|
| On
the tower, a new mounting for the spire has been installed, and the old
screed has been removed back to the top of the tower wall. |
 |
 |
| The
end of one of the main cross beams. |
 |
|
|
Wednesday 1st August
An old bees nest is removed
from a chimney and a new pot installed.
|
 |
 |
| A new
exit onto the tower roof is being constructed. Boarding of the spire is
complete - we are now waiting for the lead. |
 |
 |
| Boarding
of the gutter is complete - waiting for the lead. |
 |
|
| Sumps
are complete - new lead lining are being constructed. |
 |
 |
|
Thursday 6th September
New roof exti is complete
|
 |
|
|
New lead gutters are finished
- just a bit of tiling to do
now!
|
 |
 |
| New
lead covering on the bast of the weather vane. |
 |
|
| New
weather vane |
 |
 |
|
Thursday 18th October
Work has moved to
the south aisle
|
 |
|
| The
North facing roof has had tiles striped and the valley gutter opened up |
 |
 |
|
Thursday 7th November
The valley gutter
is waiting for metal and the roof tiles!
|
 |
 |
| |
|
|